AERL technical documentation

AERL Kakadu Combiner Box — Installation Guide Rev 2.0.1

19 pages

Download PDF Print
Download PDF· Rev 2.0.1 Installation Guide

Kakadu Combiner Box

Mounting, Cable Preparation and Power Termination

Kakadu Combiner Box
KAKADU-COMB · Kakadu 120 Installation GuideRev 2.0.1, 8 Nov 2026
aerl.com.au © 2026 AERL Pty Ltd

Contents

Document

Revision2.0.1
Effective11 / 2026
AudienceLicensed electrical workers
ProductKakadu Combiner Box (KAKADU-COMB)
BatteryKakadu 120
Start-up and shutdownKakadu 120 Installation and Operating Manual
FormatA4 · 19 pages
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

Introduction

This guide shows how to mount an AERL Kakadu Combiner Box, prepare its cable entries, and terminate the battery and load power cables ready for commissioning.

The Kakadu Combiner Box is the companion combining enclosure for the AERL Kakadu 120 battery cabinet. It parallels the DC output of up to four Kakadu 120 cabinets onto a common busbar and presents a combined output to the inverter or load equipment.

Ratings

ParameterRating
Maximum voltage500 V DC
Maximum input current150 A
Maximum output current250 A
Terminal torqueM8 · 13 N·m
Ingress protectionIP55
Dimensions (W × H × D)750 × 400 × 132 mm
Weight18 kg ±5%
Maximum cabinets supported4 × Kakadu
Busbar3 × 25 mm · 75 mm²
Mandatory input protection150 A DC MCB or 150 A HRC fuse, per input
Mandatory output protection250 A DC MCB or 250 A HRC fuse, per output
Recommended cable — battery side50 mm² with SC50-8 lugs
Recommended cable — inverter side70 mm² with SC70-8 lugs
Application1 × SPLC1202 per output

How Many Cabinets Can Be Combined

The gland plate provides eight battery input pairs (1B to 8B). Each Kakadu cabinet presents two pairs of positive and negative terminals, so the enclosure combines a maximum of four Kakadu cabinets.

Three output pairs (P1 to P3) are provided for the connection to the inverter or load equipment. Internal busbars are 3 mm × 25 mm, giving a cross-sectional area of 75 mm². Internal fusing is for short circuit protection only. Overcurrent protection shall be installed to protect both cables and bus bar.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

Typical Application

The combiner box is designed for a three-phase Selectronic SP PRO SPLC1202 system, or similar. The three outputs allow one connection to each inverter.

01

SafetyWho may install this equipment, voltage classification

The Kakadu Combiner Box carries the full combined battery current and is a live DC busbar assembly rated to 500 V DC. Read this chapter before opening the enclosure.

1.1Who May Install This Equipment

Installation, termination and commissioning must be carried out only by a licensed electrical worker competent in battery energy storage systems, and must follow AS/NZS 3000 and AS/NZS 5139.

1.2Voltage Classification

This enclosure is rated to 500 V DC and must be treated as low-voltage DC throughout. Apply low-voltage isolation, signage and access-restriction requirements in accordance with AS/NZS 3000.

The Kakadu 120 is a 140.8 V nominal battery. Establish the actual bank voltage for the system in front of you before starting work.

1.3Isolation Before Work

  1. Shut down the inverter or load equipment in accordance with its own manual.
  2. Open the battery-side isolation for every cabinet feeding the combiner box.
  3. Open the load-side isolation between the combiner box and the inverter.
  4. Prove dead at the combiner box busbars with an instrument rated for the full system voltage before touching any conductor.
  5. Apply lock-out / tag-out to every isolation point for the duration of the work.
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

1.4DC Arc Hazard

A short circuit across the combined busbar will not self-extinguish the way an AC fault does, and the severity rises sharply with system voltage. A sustained DC arc is a life-threatening hazard, not an equipment-damage risk.

Use insulated tools rated for the system voltage, remove watches and rings, and never leave a loose lug, washer or dropped fastener inside the enclosure.

Refer to AS/NZS 5139:2019 for guidance on arc flash hazard.

1.5PPE

Select PPE in accordance with AS/NZS 5139:2019 Clause 3.2.4 and Clause 3.2.4.4. As a minimum this will include insulated gloves rated for the full system voltage, eye or face protection, and arc-rated clothing appropriate to the assessed hazard. Do not work alone on an energised bank.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
02

Before You BeginPackage contents, site and mounting-surface requirements

2.1Package Contents

Unpack the combiner box and confirm all items are present and undamaged before starting. Report any transit damage to AERL before installation.

The Kakadu Combiner Box as supplied, door closed and locked. Photograph of a production unit. The key and the wall-fixing bolts are packed separately and are not shown here.
Figure 2.1 The Kakadu Combiner Box as supplied, door closed and locked. Photograph of a production unit. The key and the wall-fixing bolts are packed separately and are not shown here.
ItemQtyNotes
Kakadu Combiner Box1Front view shown in closed state
Combiner box key1Required to open the door — keep with the system documentation
Expansion bolts4Wall fixings, one per mounting point
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

2.2Site and Mounting-Surface Requirements

Manual handling

Use a two-person lift when mounting the enclosure.

Location

The enclosure measures 750 × 400 × 132 mm (W × H × D), weighs 18 kg ±5% and is rated IP55 — protected against dust and against water jets from any direction.

Choose a location that is:

Warning — not suitable for coastal installation

Do not install in coastal areas subject to salt mist.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
03

Mounting the Combiner BoxStep 1 — mark the mounting points

3.1Step 1 — Mark the Mounting Points

Mark four mounting points on the wall at a recommended height of 1.0–1.5 m above the ground, with a spacing of 773 × 250 mm.

Note — the fixing centres are wider than the enclosure

The enclosure body is 750 mm wide, but the horizontal fixing centres are 773 mm. The fixings therefore sit 11.5 mm outboard of each side of the body, on the mounting brackets — not on the back panel within the footprint.

Use a spirit level to check the enclosure is level.

Mounting setout: 773 mm horizontal fixing centres × 250 mm vertical centres, 1000–1500 mm above finished floor level.
Figure 3.1 Mounting setout: 773 mm horizontal fixing centres × 250 mm vertical centres, 1000–1500 mm above finished floor level.
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

3.2Step 2 — Verify the Hole Positions

Position the combiner box against the wall and check that the marked hole locations line up with the enclosure's mounting points.

Enclosure position and the minimum 150 mm clearance envelope required to all sides.
Figure 3.2 Enclosure position and the minimum 150 mm clearance envelope required to all sides.

3.3Step 3 — Drill and Fasten

Drill the four mounting holes, insert the supplied expansion bolts — or a suitable alternative fixing appropriate to the mounting substrate — and fasten the combiner box securely to the wall.

Check the enclosure is level once more after tightening, and confirm all four fixings are loaded evenly.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
04

Opening the EnclosureStep 4 — unlock and open the door

4.1Step 4 — Unlock and Open the Door

Use the supplied key to unlock the enclosure door.

The door lock. The supplied key is the only means of access. Keep the key in a safe place.
Figure 4.1 The door lock. The supplied key is the only means of access. Keep the key in a safe place.

Open the door fully and support it while working.

Enclosure open, showing the internal terminal arrangement.
Figure 4.2 Enclosure open, showing the internal terminal arrangement.

Before touching anything inside, re-confirm the isolation and prove dead at the busbars per Chapter 01.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
05

Preparing the Cable EntriesStep 5 — remove the lock nuts and terminal bolts

5.1Step 5 — Remove the Lock Nuts and Terminal Bolts

Remove the lock nuts fitted with the PG cable glands required for the cable installation, and remove only the M8 terminal bolts required, depending on the number of systems being combined.

Leave any unused glands and terminal bolts in place. All unused entries must stay sealed and vermin-proof.

PG cable glands and their lock nuts on the gland plate.
Figure 5.1 PG cable glands and their lock nuts on the gland plate.
The corresponding M8 terminal bolts, removed ready for the cable lugs.
Figure 5.2 The corresponding M8 terminal bolts, removed ready for the cable lugs.

Keep the removed hardware together and in a tray. A loose M8 bolt left in the base of the enclosure is a short-circuit waiting for the first vibration.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
06

Cable Sizing, Preparation and LugsCable sizing, Step 6 — pass cables through the glands first

6.1Cable Sizing

The recommended conductor sizes and lugs are:

CircuitConductorLug
Battery side — B+ / B−, input pairs50 mm²SC50-8
Inverter side — P+ / P−, output pairs70 mm²SC70-8

The selected cable must meet the requirements of AS/NZS 5139.

6.2Step 6 — Pass Cables Through the Glands First

Important

All power cables must be passed through the waterproof cable glands before the cable lugs are crimped. A crimped lug will not pass through the cable gland. Getting this out of order means cutting the lug off and re-terminating.

Work in this order for every conductor, without exception:

  1. Cut the cable to length, allowing service loop inside the enclosure.
  2. Feed the cable through its waterproof gland.
  3. Strip the conductor.
  4. Crimp the lug.
  5. Apply heat-shrink and label the cable.
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
Cable routed through the waterproof gland before the lug is crimped.
Figure 6.1 Cable routed through the waterproof gland before the lug is crimped.

Tighten each gland onto the cable once the conductor is in its final position, so the gland grips the sheath and not the insulation of a strained cable.

6.3Step 7 — Crimp the Cable Lugs

Crimp cable lugs onto the power cables. All cable lugs are secured using M8 bolts, torqued to 13 N·m on final assembly (see Chapter 07).

Crimp with the correct die for the lug, apply the full number of crimps for the barrel length, and finish each barrel with adhesive heat-shrink. Confirm every crimp with a pull test before installing the cable.

Cable lugs crimped onto the prepared power cables.
Figure 6.2 Cable lugs crimped onto the prepared power cables.
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
07

Power ConnectionsStep 8 — terminate the power cables

7.1Step 8 — Terminate the Power Cables

Connect all B+, B−, P+ and P− power cables to their designated entry positions and terminals.

The gland plate is divided into four labelled groups:

GroupPositionsFunction
INPUT+1B+ to 8B+Battery positive — two positions per Kakadu cabinet
INPUT−1B− to 8B−Battery negative — two positions per Kakadu cabinet
OUTPUT+P1+, P2+, P3+Combined positive to the load / inverter
OUTPUT−P1−, P2−, P3−Combined negative to the load / inverter

An earth point is provided at the left-hand end of the plate.

Gland plate layout: cable entry positions and their grouping.
Figure 7.1 Gland plate layout: cable entry positions and their grouping.

7.2Step 9 — Mandatory Input and Output Overcurrent Protection

Mandatory — all input and output cables must be protected

Each combiner input must be protected by a 150 A DC MCB or a 150 A HRC fuse, fitted on the battery feed upstream of the combiner. Each combiner output must be protected by a 250 A DC MCB or a 250 A HRC fuse, fitted on the inverter feed downstream of the combiner.

Each output supplies a maximum of one Selectronic SP PRO SPLC1202. Do not connect a load with >250 A continuous current rating.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
DutyDeviceLocation
Short circuitCombiner's internal fuseBusbar origin, inside the enclosure
OverloadKakadu BMS DC MCBBattery Output, upstream
Overload150 A DC MCB or 150 A HRC fuseEach battery input, upstream
Overload250 A DC MCB or 250 A HRC fuseInverter feed, downstream

Note: The combiner's internal fuse cannot provide overload protection for the busbar — its rating is far above the busbar's continuous rating. The downstream device carries the whole of the busbar's load current and is what protects it against overload. Omitting it leaves the busbar without overload protection.

AS/NZS 4509, AS/NZS 5139 and the manufacturer's guidelines must be followed for electrical protection.

Working practice at the busbar:

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
08

Closing Up and CommissioningBefore closing the door, electrical verification

Complete these checks before the bank is energised.

8.1Before Closing the Door

  1. Confirm every M8 terminal connection is torqued to 13 N·m and torque-sealed.
  2. Confirm polarity on all B+, B−, P+ and P− conductors.
  3. Confirm every input in use has a 150 A DC MCB or a 150 A HRC fuse fitted, and every output in use a 250 A DC MCB or a 250 A HRC fuse.
  4. Confirm all glands are tightened onto the cable sheath and all unused entries are sealed.
  5. Confirm all unused terminal bolts remain fitted.
  6. Remove all tools, offcuts, swarf and loose hardware from the enclosure.
  7. Confirm all cable labels are fitted and legible, identified to the cabinet each pair serves.

8.2Electrical Verification

  1. Carry out an insulation resistance test between each pole and earth with the battery cabinets isolated, in accordance with AS/NZS 3000.
  2. Confirm continuity of the protective earthing conductor to the enclosure.
  3. Confirm no continuity between poles.

Refer to the Kakadu 120 Installation and Operating Manual for the start-up and shutdown sequence.

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
09

Quick Checklist

Step
1Isolate and prove dead with an instrument rated for the full system voltage. Lock out every isolation point.
2Confirm package contents: combiner box, key, 4 × expansion bolts.
3Mark four mounting points, 1.0–1.5 m above ground, 773 × 250 mm spacing.
4Offer the box up and verify hole positions before drilling. Two-person lift — 18 kg.
5Drill, fit expansion bolts, fasten the box level and secure on all four fixings.
6Unlock and open the door. Re-check dead at the busbars.
7Count the pairs needed — two per cabinet — then remove only the required lock nuts and M8 bolts.
8Pass every cable through its gland before crimping any lug.
9Crimp lugs sized to the designer's cable schedule.
10Terminate B+, B−, P+ and P− per the gland plate layout. Torque M8 to 13 N·m and torque-seal.
11Confirm a 150 A DC MCB or 150 A HRC fuse fitted on every input in use, and a 250 A DC MCB or 250 A HRC fuse on every output in use.
12Verify polarity, clear the enclosure, insulation test, close and lock.
13Refer to the Kakadu 120 Installation and Operating Manual for the start-up and shutdown sequence.
AERL Kakadu Combiner Box · Installation GuideRev 2.0.1
10

Warranty and SupportWarranty, support, change log

10.1Warranty

The Kakadu Combiner Box warranty is 2 years, starting 30 days after AERL dispatches the product. Conditions apply: see the Kakadu 120 Battery and Combiner Box Warranty Statement, at aerl.com.au.

10.2Support

Before you contact AERL, note the number of Kakadu cabinets combined, the inverters connected and what the Kakadu HMI shows. Contact AERL support on 1800 950 865 or [email protected].

10.3Change Log

RevisionDateChange
2.0.009 / 2026First release.
2.0.111 / 2026Re-issued in the new AERL document design. Steps 6 and 7 put in working order (cables through the glands before the lugs are crimped, as the Important note and the quick checklist require); AS/NZS 5139 added to who may install; the Kakadu 120 manual named by its title; checklist items numbered in sequence; warranty term added; the mandatory 150 A input protection (Ratings) added to Step 9 and both checklists; text limited to the Kakadu 120.

Thank You for Choosing AERL

If you have any questions or need support, contact AERL.

Sincerely,

The AERL Team

AERL Pty Ltd · 1/75 Bluestone Circuit, Seventeen Mile Rocks QLD 4073 · 1800 950 865 · [email protected] · aerl.com.au

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

Notes

AERL Kakadu Combiner Box · Installation GuideRev 2.0.1

Australian Energy Research Laboratories

Address

1/75 Bluestone Circuit
Seventeen Mile Rocks QLD 4073
Australia

Contact

[email protected]
[email protected]

aerl.com.au Phone1800 950 865