# Kakadu Commissioning Guide · SP PRO SPLC1202 & CoolMax SRX

*Rev 1.1.6. Markdown copy of the AERL document at https://www.aerl.com.au/docs/kakadu-commissioning-guide-splc1202-srx; the PDF (https://www.aerl.com.au/documents/guides/AERL_Kakadu_Commissioning_Guide_SPLC1202_SRX_REV_116.pdf) is the controlled version.*

Commissioning Guide

# Kakadu with Selectronic SP PRO SPLC1202 & AERL CoolMax SRX

Control Philosophy, Hardware, Connections and SP LINK Set-Up

**AERL Kakadu · Rev 1.1.6**

| | |
|---|---|
| Revision | 1.1.6 |
| Effective | 11 / 2026 |
| Audience | Licensed electrical workers |
| Battery | Kakadu 120 (managed) |
| Inverter | SP PRO SPLC1202 |
| Charge controller | CoolMax SRX 120 |
| EMS | AERL Nexus Gateway |
| SP LINK battery type | BMS – SelectCell River Gum |
| CAN cable at SP PRO | SP PRO to BMS cable |
| SoC source | Kakadu BMS via CAN |
| CAN bus | SP PRO → Nexus → SRX → Kakadu |
| Nexus → SP PRO | CAN + RS485 Modbus RTU |

## In This Guide

## Introduction

This guide covers the system-level commissioning of a Kakadu 120 battery bank operating with Selectronic SP PRO SPLC1202 inverters and AERL CoolMax SRX 120 DC-coupled MPPT charge controllers. It sets out AERL's recommended control philosophy, the hardware required, how the communications are connected, and the settings to program into the Nexus and the SP PRO.

It does not replace the product manuals. Install each item in accordance with its own documentation first.

### Reference Documents

| Document | Use it for |
|---|---|
| AERL Kakadu 120 Installation and Operating Manual, V1.1.1 | Cabinet installation, BMS chain, Master Unit / Last Unit settings |
| AERL Kakadu Combiner Box Installation Guide, Rev 2.0.1 | DC paralleling of cabinets to the inverters |
| AERL Nexus installer guide — Selectronic SP PRO → AERL Cloud, Rev 1.0.1 | Nexus wiring, getting online, claiming, adding the SP PRO |
| Selectronic SP PRO Manual (OI0003, Rev 47) | Inverter installation and operation |
| Selectronic SP LINK Manual (OI0005, Rev 31) | SP LINK configuration settings |

> **Who may commission this system**
>
> Installation, termination and commissioning must be carried out only by a licensed electrical worker competent in battery energy storage systems, in accordance with AS/NZS 3000 and AS/NZS 5139.

> **What has changed**
>
> Since Rev 1.0.0 the SP PRO runs the Kakadu as a managed battery (battery type **BMS – SelectCell River Gum**); the Rev 1.0.0 *Custom* battery settings and SP LINK configuration file no longer apply. Cables made to Rev 1.1.5 or earlier used the wrong BMS-end CAN pins (now 4 and 5, section 3.4) — check them.

## Chapter 01 Control Philosophy

AERL recommends the following control philosophy for the Kakadu battery.

- **The AERL Nexus Gateway is the EMS for the entire system.**
- **The Kakadu is a managed battery.** Its master BMS broadcasts the battery's safe operating window over CAN bus.
- **The SP PRO SPLC1202 runs the Kakadu as a managed battery** , with SP LINK battery type *BMS – SelectCell River Gum* . It reads the Kakadu's CAN data directly, and the SelectCell River Gum profile applies the correct voltage and charge settings.
- **The Nexus monitors the SP PRO and sends target charge control points to the CoolMax SRX.**
- **The CoolMax SRX charges from solar** to the target charge control points set by the Nexus.

![Logical control flow: the Kakadu master BMS broadcasts its limits on CAN to the SP PRO and the Nexus; the Nexus monitors the SP PRO and sends target charge control points to the CoolMax SRX; the generator is an AC source for the SP PRO.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-fig1-1-control-philosophy.svg)

**Figure 1.1** Logical control flow. The Kakadu broadcasts its limits on the CAN bus. The SP PRO operates within them, and the Nexus monitors the SP PRO and directs the SRX.

### Roles

| Component | Role in the system | Link |
|---|---|---|
| Kakadu 120 master BMS | Managed battery. Broadcasts the safe operating window: charge voltage limit, charge and discharge current limits, SoC and alarms. | CAN 2.0A |
| SP PRO SPLC1202 | Inverter, AC source management and generator charger. Managed battery type *BMS – SelectCell River Gum*. Charges and discharges within the Kakadu's limits. | CAN 2.0A (end of the bus). RS485 Modbus RTU to the Nexus |
| AERL Nexus Gateway | System EMS. Monitors the SP PRO and sends target charge control points to the SRX. Telemetry to AERL Cloud. | CAN (mid-bus). RS485 Modbus RTU to the SP PRO (Nexus is the only master) |
| CoolMax SRX 120 | DC-coupled solar charging to the Nexus target charge control points | CAN |
| Generator | AC source for the SP PRO | Started by the SP PRO according to its Generator Auto Start settings |

### State of Charge

With a managed battery type, the SP PRO takes the battery SoC directly from the Kakadu BMS. No SP PRO DC shunt is needed on the SRX output.

## Chapter 02 Required Hardware

### 2.1 Bill of Materials

| Item | Quantity | Notes |
|---|---|---|
| **AERL Nexus Gateway** | **1 per system** | One Nexus covers the whole site. Do not put a second gateway, data logger or remote screen on the same SP PRO Modbus link. |
| **AERL CoolMax SRX 120** | **Minimum 1 per Kakadu cabinet** | Size the PV array for each SRX according to its datasheet. |
| AERL Kakadu 120 cabinet | 1 to 16 | Two strings (two BMS) per cabinet |
| Selectronic SP PRO SPLC1202 | As designed | For example, 1 for single-phase or 3 in PowerChain for three-phase |
| AERL Kakadu Combiner Box | As required | Parallels up to 4 cabinets, with one output per SPLC1202. See the Combiner Box guide. |
| RS485 patch lead | 1 | Straight-through CAT5e or CAT6, Nexus RS485 to SP PRO ACC Port 1. Keep it short. |
| SP PRO to BMS cable | 1 | SP PRO CAN socket to Nexus `CAN 2`. Not a straight-through lead (section 3.4). |
| CAN leads | 1 per hop | Shielded CAT5e or CAT6, made to length: Nexus → SRX → … → Kakadu master BMS INV |
| CAN termination | — | No terminator plugs needed. The Kakadu BMS terminates automatically, the SP PRO uses a DIP switch on its comms card, and each SRX has a CANBUS 120 Ω switch (section 3.1). |
| Ethernet lead | 1 | Nexus ETH to the site router |
| Laptop with Selectronic SP LINK | 1 | Must be a version of SP LINK that lists the battery type *BMS – SelectCell River Gum* |

### 2.2 SP PRO Prerequisites

Check the following in SP LINK under **Data View → Inverter Details** before you connect the Nexus.

| # | Requirement |
|---|---|
| 1 | The inverter is a Series 2i, or an equivalent newer model. |
| 2 | The Comms Card (ACC) revision is 8 or higher. |
| 3 | The SP PRO firmware is V14.47 or newer. |
| 4 | The ACC firmware is V4.31 or newer. |
| 5 | SP LINK offers **BMS – SelectCell River Gum** under Battery Type. If it does not, update SP LINK and the SP PRO firmware before you continue. |

> **EMS firmware**
>
> The Nexus Gateway and every CoolMax SRX must run AERL's EMS firmware for this control philosophy. AERL installs it remotely during commissioning (section 4.1.2).

## Chapter 03 Connections

Two communication links make up the control system.

- **CAN bus** (CAN 2.0A): **SP PRO → Nexus → CoolMax SRX → Kakadu**
- **RS485** (Modbus RTU): **Nexus → SP PRO** , for monitoring

| From | To | Link | Cable | Notes |
|---|---|---|---|---|
| SP PRO `CAN` | Nexus `CAN 2` | CAN 2.0A | SP PRO to BMS cable (section 3.4) | The SP PRO is one end of the bus: set the CAN termination DIP switch on its comms card to ON. On a PowerChain system, connect to the master only. |
| Nexus `CAN 1` | CoolMax SRX (last in chain) `CAN` | CAN 2.0A | Shielded CAT5e/CAT6 | Nexus CAN 1 and CAN 2 are linked internally and the Nexus has no built-in termination. Here it sits mid-bus, so fit no termination plug. |
| CoolMax SRX `CAN` | Next CoolMax SRX `CAN` | CAN 2.0A | Shielded CAT5e/CAT6 | Daisy-chain every SRX on the same bus. Set the CANBUS 120 Ω switch on every SRX to OFF. |
| CoolMax SRX (first in chain) `CAN` | Kakadu master BMS `INV` | CAN 2.0A | Shielded CAT5e/CAT6 | The other end of the bus. The Kakadu BMS terminates automatically. |
| BMS `OUT` | Next BMS `IN` | Kakadu BMS chain | Made to length | See Kakadu 120 manual, step 7 and §5.5. |
| Nexus `RS485` | SP PRO ACC `Port 1` | RS485 · Modbus RTU | Straight-through CAT5e/CAT6 | Slave 1, 9600 baud, 8N1. The Nexus is the only Modbus master. On a PowerChain system, connect to the master only. |
| Nexus `ETH` | Site router | Ethernet | CAT5e/CAT6 | Connects automatically to AERL Cloud |

### 3.1 Rules for the Communications Wiring

1. **One CAN bus.** The Kakadu, the SRX units, the Nexus and the SP PRO share a single CAN bus. Its order is SP PRO → Nexus → SRX → Kakadu.
2. **CAN bus termination.** The two ends of the bus are the SP PRO and the Kakadu master BMS, and each needs 120 Ω termination. Nothing in between should be terminated. | Device | Position on the bus | Termination setting |
|---|---|---|
| SP PRO (PowerChain master) | End | CAN termination DIP switch on the comms card **ON** |
| AERL Nexus Gateway | Mid-bus | None (no built-in termination; at a bus end, fit a 120 Ω plug in its spare CAN socket) |
| CoolMax SRX (every unit) | Mid-bus | CANBUS 120 Ω switch **OFF** |
| Kakadu master BMS | End | Automatic — nothing to set |

3. **Master BMS.** The BMS whose `INV` port connects to the CAN bus is the master. Leave its **Master Unit** LED lit and turn it off on every other BMS. Leave **Last Unit** lit on the final string in the chain only (Kakadu 120 manual §6.3 and §6.4).
4. **PowerChain master only.** On a PowerChain system, connect the CAN bus and the RS485 lead to the PowerChain master only. The other inverters receive battery data over Selectronic's PowerChain link.
5. **Cabling practice.** Mount the Nexus as close as possible to the SP PRO, so that the RS485 run is short. Use shielded CAT5e/CAT6 for CAN, with the shield earthed at one end only. Keep comms cables separated from DC power runs. Contact AERL for any CAN run longer than about 100 m.

### 3.2 Simple System — 1 × Nexus, 1 × SPLC1202, 1 × CoolMax SRX

![Simple system wiring: one Kakadu 120 cabinet, one CoolMax SRX 120, one SP PRO SPLC1202 and one Nexus Gateway, showing the CAN bus, RS485, Ethernet and DC/AC power connections.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-fig3-1-simple-system.svg)

**Figure 3.1** One Kakadu 120 cabinet, one CoolMax SRX 120, one SP PRO SPLC1202 and one Nexus Gateway. The CAN bus runs from the master BMS `INV` port through the SRX and the Nexus to the SP PRO. RS485 runs from the Nexus to ACC Port 1.

### 3.3 Multi-cabinet Example — 4 × Kakadu, 4 × SRX, 3 × SPLC1202

![Multi-cabinet example: four Kakadu 120 cabinets with eight BMS, four CoolMax SRX 120 units daisy-chained on CAN, one Nexus Gateway and three SP PRO SPLC1202 inverters in a three-phase PowerChain.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-fig3-2-multi-cabinet.svg)

**Figure 3.2** Four cabinets (8 BMS) through one Kakadu Combiner Box to a three-phase PowerChain of SPLC1202s. The CAN bus runs master BMS `INV` → SRX 1 → SRX 2 → SRX 3 → SRX 4 → Nexus → SP PRO L1. The same pattern scales to 16 cabinets, with at least one SRX per cabinet.

### 3.4 SP PRO to BMS Cable

The SP PRO and the Kakadu BMS use different RJ45 pins for CAN. Connect the SP PRO to the CAN bus with the SP PRO to BMS cable, which re-maps the pins. **A standard straight-through patch lead will not work.**

Plug the SP PRO end into the SP PRO CAN socket (the PowerChain master on a PowerChain system). Plug the BMS end into Nexus `CAN 2`.

| SP PRO end — pin | SP PRO end — signal | BMS end — pin | BMS end — signal |
|---|---|---|---|
| 1 | **CAN_H** | 4 | **CAN_H** |
| 2 | **CAN_L** | 5 | **CAN_L** |
| 4 | — | 1 | — |
| 5 | — | 2 | — |
| 3, 6, 7, 8 | — | Not connected | — |

Pins 1/2 at each end cross to pins 4/5 at the other end, as shown in Selectronic's *BMS to SP PRO CAN Bus cable* application note. The cable is symmetrical and works either way round. CAN_H / CAN_L are on pins 1 / 2 at the SP PRO and on pins 4 / 5 at the Nexus `CAN 2` socket.

![SP PRO to BMS cable pinout: SP PRO end pins 1 and 2 cross to BMS end pins 4 and 5, and BMS end pins 1 and 2 cross to SP PRO end pins 4 and 5; pins 3, 6, 7 and 8 are not connected.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-fig3-3-sppro-bms-cable.svg)

**Figure 3.3** SP PRO to BMS cable pinout, both directions.

If you make the cable up yourself, keep CAN_H and CAN_L on one twisted pair, and check every pin for continuity against the table before you fit it.

## Chapter 04 Set-Up

### 4.1 AERL Nexus Gateway

#### 4.1.1 Set up the Nexus as normal

Follow the AERL Nexus installer guide *Selectronic SP PRO → AERL Cloud* (Rev 1.0.1). In summary:

1. Connect the Nexus `RS485` socket to SP PRO ACC `Port 1` with a straight-through CAT5e/CAT6 patch lead.
2. Connect the CAN bus as described in Chapter 03.
3. Connect Ethernet from the site router, then power the Nexus on. It connects to AERL Cloud automatically.
4. At **aerl.cloud** , click **Add Gateway** on the Gateways page (or **+** in the top bar). On **Claim Your Gateway** , enter the serial number and pin code from the Nexus label and click **Claim Gateway** , then assign the gateway to a location.
5. In **Gateways** , choose **Manage** on your Nexus to open **Edit Gateway** , then **Modbus Devices → Add Device** ; set **Device Product** to **Selectronic SP PRO** and click **Add Device** . You need the Owner or Admin role. The configuration applies within about five minutes.

The Kakadu BMS and the CoolMax SRX units on the CAN bus are discovered automatically.

#### 4.1.2 EMS firmware push — contact AERL

Once the Nexus is online and claimed, **contact AERL technical support to push the EMS firmware to the Nexus and the CoolMax SRX units.** Have the following ready:

- the Nexus serial number
- the serial number of every CoolMax SRX
- the number of Kakadu cabinets, and the SP PRO configuration (single inverter or PowerChain)
- the site name and location as claimed in AERL Cloud.

AERL confirms when the push is complete. Then check in AERL Cloud that the Kakadu and every SRX are reporting.

### 4.2 Setting up the CoolMax SRX

Set up every CoolMax SRX on the site with AERL Link:

1. Download and install the latest version of **AERL Link** , then connect to the SRX.
2. Change the **preset** to **Kakadu** .
3. Change the **Battery Type** to **Kakadu** .
4. Check that the charge settings match Figure 4.1, then save the settings to the SRX.

Also set the CANBUS 120 Ω switch on every SRX to **OFF** (section 3.1).

![AERL Link charge settings screen for a CoolMax SRX with the Kakadu preset and Battery Type Kakadu selected.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-aerl-link-srx-kakadu.png)

**Figure 4.1** AERL Link charge settings for the CoolMax SRX with the Kakadu preset and battery type.

### 4.3 SP PRO — System → Communication (Modbus to the Nexus)

![SP LINK System, Communication settings page.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-splink-communication.png)

**Figure 4.2** System → Communication.

| Setting | Value |
|---|---|
| Port 1 Baud Rate | 57600 |
| Port 1 DTR/DCD | Enabled |
| Port 1 Comm Card Input | Internal (RJ45) |
| Port 2 Baud Rate | 9600 |
| Port 2 DTR/DCD | Enabled |
| **Modbus RTU Port** | **9600 · 8 bit · None · 1 stop** |
| **Modbus RTU Address** | **1** |

These Modbus settings must match what the Nexus expects: slave 1, 9600 baud, 8N1.

### 4.4 Save, Upload and Site-Specific Settings

1. Confirm the SP LINK Battery Type is **BMS – SelectCell River Gum** (Figure 4.3).
2. Save the configuration and upload it to the SP PRO.
3. In SP LINK, open **Data View → Battery Management** and confirm that the Kakadu BMS data is shown. This view is only available with a managed battery.
4. Confirm in AERL Cloud that SP PRO data appears on the Nexus within about five minutes.

![SP LINK Battery Type drop-down set to BMS – SelectCell River Gum.](https://www.aerl.com.au/docs/_assets/assets/images/kakadu/kakadu-cg-splink-battery-type-rivergum.png)

**Figure 4.3** SP LINK Battery Type set to BMS – SelectCell River Gum.

> **Site-specific parameters**
>
> Installers must set up all other parameters as required for their site. These include unit application, nominal AC voltage and frequency, AC source power, generator controller settings, generator schedule start, AC input, power quality / DRM, inputs and outputs, and PowerChain settings.

### 4.5 Final Checks

| # | Check |
|---|---|
| 1 | Kakadu master BMS **Master Unit** LED is lit, and **Last Unit** is lit on the final string only. |
| 2 | CAN bus runs SP PRO → Nexus → SRX … → Kakadu master BMS `INV`. The SP PRO connects through the SP PRO to BMS cable. |
| 3 | SP PRO CAN termination DIP switch ON. Every SRX CANBUS 120 Ω switch OFF. No termination plug at the Nexus (mid-bus). |
| 4 | RS485 runs from the Nexus to ACC `Port 1` on the SP PRO (PowerChain master). The Nexus is the only Modbus master. |
| 5 | Nexus is claimed in AERL Cloud, and the Selectronic SP PRO Modbus device has been added. |
| 6 | AERL has confirmed the EMS firmware push to the Nexus and every SRX. |
| 7 | Every SRX is set up in AERL Link with the **Kakadu** preset and Battery Type **Kakadu**. |
| 8 | SP LINK: Battery Type *BMS – SelectCell River Gum*. |
| 9 | SP LINK **Data View → Battery Management** shows the Kakadu BMS data. |
| 10 | Kakadu, every SRX and the SP PRO are all reporting in AERL Cloud. |
| 11 | Site-specific parameters, including generator control, have been set. |

## Chapter 05 AERL Technical Support

#### AERL support

Email: [support@aerl.com.au](mailto:support@aerl.com.au)

Phone: **1800 950 865**

Web: [aerl.com.au](https://www.aerl.com.au)

#### Address

AERL 1/75 Bluestone Circuit Seventeen Mile Rocks QLD 4073 Australia

### When You Contact AERL, Include

- the site name, and the Nexus serial number
- the serial numbers of the CoolMax SRX units, and the number of Kakadu cabinets
- the SP LINK *Inverter Details* and *Battery Management* screenshots, and the exported SP LINK configuration file
- a short description of what you see, including the Nexus Tx/Rx LEDs if the issue is with RS485 comms.