AERL technical documentation

Solinteg M2HT 25–50 kW — Quick Start Guide Rev 1.0.2

13 pages

Download PDF Print
Download PDF· Rev 1.0.2 Quick Start Guide

Solinteg M2HT 25⁠–⁠50 kW Hybrid Inverter

Three-Phase High-Voltage Hybrid Inverter

Solinteg M2HT 25–50 kW Hybrid Inverter
M2HT-25K · 29.9K · 30K · 40K · 50K Quick Start GuideRev 1.0.2, 9 Nov 2026
aerl.com.au Australian edition

Contents

Document

Revision1.0.2 (Australian edition)
Effective11 / 2026
AudienceLicensed installers
Full detailsSolinteg M2HT 25–50 kW User Manual
FormatA4 · 13 pages
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
01

Before You StartWhat you need, key values at a glance

This guide covers the essential steps to install, connect and start up the Solinteg M2HT 25–50 kW hybrid inverter. It does not replace the Solinteg M2HT 25–50 kW User Manual. Read the manual's safety instructions (§1) before you start, and use it for any step you are unsure of. References such as §5.4 point to the user manual.

Only licensed electrical workers may install the inverter

Install in accordance with AS/NZS 3000, AS/NZS 4777.1, AS/NZS 4777.2, AS/NZS 5033 and AS/NZS 5139, and the requirements of the local network service provider. Connect to the grid only with network approval. Never work on live equipment: isolate every supply first. Connect the protective earth before anything else.

High DC voltages

The PV array produces dangerous DC voltage in sunlight. PV strings must not exceed 950 V (above 1000 V the inverter is damaged). The battery must not exceed 840 V. Wait 10 minutes after isolating before touching internal parts.

Parallel systems

For a parallel system, see §5.10 and contact AERL when designing it.

1.1What You Need

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2

1.2Key Values at a Glance

ItemValueManual
Inverter size (W × H × D)919 × 739 × 305 mm, 89 kg, IP66§11
Clearances300 mm above, 450 mm below, 600 mm each side; 600 mm between inverters§4.1
MountingVertical only, on a wall that can carry the weight; out of direct sun and rain§4.1
On-grid AC cable5-core, 16–50 mm², 20–37 mm OD; strip sheath 95–100 mm, cores 20–25 mm§5.4
On-grid connector torquesLugs 3.8 N·m; connector nut 10 N·m§5.4
Back-up / generator AC cable5-core, 10–25 mm² flexible or 10–35 mm² rigid; strip cores 15 mm; screws 5 N·m, nut 10 N·m§5.4
PV cable4 or 6 mm², 5.9–8.8 mm OD; strip 7 mm§5.5
PV voltage950 V operating max.; 1000 V absolute§5.5
Battery cable50 mm², 13 mm OD; strip 16.5 mm§5.6
Battery voltage150–840 V; fuses in both conductors§5.6
Communication terminals0.5–1.5 mm²; strip sheath 55 mm, cores 8 mm; 1.2 N·m§5.9
Breakers (on-grid / back-up)25K: 100 / 63 A · 29.9K and 30K: 125 / 80 A · 40K: 160 / 100 A · 50K: 160 / 125 A§5.2
RCDs30 mA type A on the load circuits§5.2
Operating temperature−30 to 60 °C (derating above 45 °C)§4.1
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
02

Mount the InverterChoose the location, mount and earth

2.1Choose the Location

Choose a shaded, sheltered location.
Figure 2.1 Choose a shaded, sheltered location.
Clearances around a single inverter.
Figure 2.2 Clearances around a single inverter.

2.2Mount and Earth

  1. Level the bracket, mark and drill the holes (830 mm and 45 mm spacings), and fix the bracket to the wall (§4.4).
  2. Fit the lifting handles, lift the inverter onto the bracket with two people or a hoist, and secure it with the M6 screws (§4.3).
  3. Connect the external earth terminal (lower right) to the earth bar with a crimped OT lug, before any other cable (§4.5).
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
Bracket drilling dimensions.
Figure 2.3 Bracket drilling dimensions.
Hanging the inverter.
Figure 2.4 Hanging the inverter.
External earth connection.
Figure 2.5 External earth connection.
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
03

Wire the SystemAC connections, PV strings, battery

Before you connect anything

Switch off all AC breakers, the battery breaker and the inverter DC switch. Check every cable is dead. Do not switch on any breaker until all connections are complete.

3.1AC Connections

In Australia the neutral must not be switched, and the grid-side and back-up neutrals must be connected together (AS/NZS 3000). Fit a separate breaker on each AC output; never connect loads directly to the inverter. Do not confuse the back-up and generator connectors (§5.2, §5.4).

Wiring diagram for Australia and New Zealand.
Figure 3.1 Wiring diagram for Australia and New Zealand.
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
  1. On-grid: remove seal parts to suit the cable, strip the cable, crimp OT lugs, fit L1–L3 then N/PE with their insulating spacers (3.8 N·m), assemble the housing and tighten the nut to 10 N·m.
  2. Back-up and generator: strip the cores 15 mm, fit ferrules to stranded cores, insert in the marked order (5 N·m), push on the housing until it clicks and tighten the nut to 10 N·m.
On-grid connector seal parts.
Figure 3.2 On-grid connector seal parts.
Connecting the on-grid cable.
Figure 3.3 Connecting the on-grid cable.

3.2PV Strings

  1. Assemble the PV connectors: strip 7 mm, crimp, click into the housing, tighten the nut (§5.5).
  2. Turn the DC switch OFF and check each string's polarity and open-circuit voltage: no more than 950 V.
  3. Plug the strings into the DC inputs until they click. Cap unused inputs.

Fit an external DC isolator to AS 60947.3:2018 and AS/NZS IEC 60947.1:2020 where required.

DC switch OFF.
Figure 3.4 DC switch OFF.
Checking the string voltage.
Figure 3.5 Checking the string voltage.
Connecting the strings.
Figure 3.6 Connecting the strings.
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2

3.3Battery

  1. Measure the battery voltage: no more than 840 V. Check polarity.
  2. Strip 16.5 mm, crimp the contacts with a hydraulic crimper, tighten the connector nuts (§5.6).
  3. Plug the positive and negative connectors into the battery terminals until they click.
Crimping the battery contact.
Figure 3.7 Crimping the battery contact.
Connecting the battery.
Figure 3.8 Connecting the battery.

3.4Meter, CTs and Communication

Meter and CT wiring.
Figure 3.9 Meter and CT wiring.
Plugging COM2 and COM3 into the inverter.
Figure 3.10 Plugging COM2 and COM3 into the inverter.
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
04

Start up and CheckChecks before start-up, start-up, check the indicators

4.1Checks Before Start-Up

4.2Start-Up

StepAction
1Switch on the AC breaker
2Switch on the battery, and power up the battery pack if required
3Turn on the DC switch, then wait 5 minutes
4Set the safety code to the AS/NZS 4777.2 region your network requires, and the battery ID to the battery fitted
5The inverter connects to the grid when conditions are met (this can take several minutes)
6Check the indicators, then run the CT auto test and an SOC reset from the app

4.3Check the Indicators

IndicatorRunning normally
Power (blue)Breathing
GridOn steady (on-grid)
CommunicationGreen
Communication orange / redNo meter / no BMS communication
Power redAlarm: check the display
Indicators, display and button.
Figure 4.1 Indicators, display and button.
Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
05

Connect to the IntegHub App

Scan a code to install the free Solinteg IntegHub app, or search for IntegHub in Google Play or the App Store.

Get the IntegHub app
QR code: Android Google Play
Android
Google Play
QR code: iPhone App Store
iPhone
App Store
  1. Log in to IntegHub and create a plant.
  2. Open the plant, tap Devices, then +.
  3. Tap Scan to add and scan the QR code on the inverter rating plate, or tap Enable Bluetooth to find it.
  4. Select the inverter, choose Wi-Fi or LAN and enter the network details.
  5. Wait for configuration to finish, tap Complete, name the device and tap Confirm.

The safety code, protection and power quality settings are password protected. Contact AERL support for the password (§7.6).

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
06

Shut Down, Alarms and SupportShut-down, common faults

6.1Shut-Down

  1. Stop the inverter from the app or the display.
  2. Switch off the grid and load breakers.
  3. Switch off the battery and battery DC breaker.
  4. Wait 30 seconds, turn the DC switch OFF, then wait 10 minutes before working on the inverter.

6.2Common Faults

MessageMeaningFirst check
BMS Comm FaultNo BMS communicationBattery ID setting; cable in BMS 1 (not BMS 2); battery status
Meter Comm FaultNo meter communicationMETER cable and connections; compatible meter model
PV Over VoltagePV voltage above the limitReduce modules per string so Voc stays below the maximum
ISO Over LimitationDC insulation resistance too lowPV modules, cables and connectors for water or damage; insulation ≥ 500 kΩ
Grid Voltage FaultGrid voltage outside the safety code limitsSafety code; AC wiring; voltage rise from undersized AC cable
Backup Load FaultBack-up load above capacityReduce the back-up load; check battery capacity
Over TemperatureInverter too hotVentilation and clearances; let it cool, then restart

The full list of status codes and faults is in §8 of the user manual.

AERL technical support

1800 950 865 · [email protected] · aerl.com.au

Have ready: the inverter model and serial number, the installation date, the fault message and when it occurred, and photos of the installation.

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2

Notes

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2

Notes

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2

Notes

Solinteg M2HT 25–50 kW · Quick Start GuideRev 1.0.2
Manufactured by Solinteg
Supplied and supported in Australia by AERL

Australian Energy Research Laboratories

Address

1/75 Bluestone Circuit
Seventeen Mile Rocks QLD 4073
Australia

Contact

[email protected]
[email protected]

aerl.com.au Phone1800 950 865